<img height="1" width="1" style="display:none;" alt="" src="https://px.ads.linkedin.com/collect/?pid=1964316&amp;fmt=gif">

Allied Fiber Southeastern Segment Update: Fiber Jetting in Florida Underway

Construction for the Miami-Jacksonville-Atlanta segment of Allied Fiber’s Southeastern route is underway. Allied Fiber is currently jetting up to 340 feet of fiber per minute (5.6 miles of fiber per day). The Miami to West Palm Beach segment is expected to be completed during the first week of August 2013. The Miami-Jacksonville-Atlanta build is anticipated to take 6 to 9 months to complete.

Figure Eight Cable in Lantana

Allied Fiber’s Southeastern route marks the first network-neutral, fully integrated, nationwide dark fiber and colocation system in the United States.

In early April, Allied Fiber and Corning Fiber Systems agreed to terms allowing Allied Fiber to issue a purchase order for a custom-built 528 count fiber cable, which was an integral element in making the Miami-Jacksonville-Atlanta build a reality.

For additional information regarding the Miami-Jacksonville-Atlanta portion of Allied Fiber’s Southeastern route, please click here.

Allied Fiber Construction Photos July 2013

The following gallery of images were taken during the fiber construction/cable jetting at Lantana.

Excavation near Lantana

Figure Excavation in Lantana

First Manhole in Lantana

Rope Cutting in Lantana

Backlifting in Lantana

Fiber reel staging

 

 

 

 

 

 

Opening manhole to jet

Jetting the cable at 260+ feet per minute

Adding lube to jetting

 

 

 

 

 

 

Pulling cable from the reel and into jetting machine

Jetting machine setup

Jetting machine setup

Share This Article